Saturday, December 13, 2025
7.6 C
Srinagar

Restoration work on Amarnath Yatra track to be completed by June 15: BRO

Srinagar, June 3:  The Border Roads Organisation on Saturday said that it will complete the restoration works on Amarnath Yatra track by Jun 15 even as the Yatra is scheduled to commence from July 1.

In a statement, a spokesperson said that Amarnath Yatra tracks were handed over to BRO in September 2022 for further maintenance and upgradation.

“Earlier the yatra track from Baltal to Holy Cave was maintained by PWD (R&B) and the one from Chandanwari to Holy Cave was maintained by Pahalgam Development Authority. Restoration works on the tracks could however, commence only in March 2023 after the necessary funds were released to BRO by the government. The basic scope of work involved snow clearance, widening of the track, restoration of all foot bridges, fixing of hand rails, protection works at slide prone stretches and construction of breast walls and retaining walls for protection of the track.”

It reads that BRO has been asked to complete the restoration works by June 15 as the Yatra is set to commence wef 01 Jul 2023.

It further added that snow clearance, using plant machinery, commenced on both the tracks from Baltal and Chandanwari in the last week of March.

“Concurrent to the progress of snow clearance of the tracks, additional plant equipment and manpower were employed for other restoration works. As on date, eight dozers/ excavators and almost 1100 labours are working on the tracks. Though, unprecedented snow and rain in the higher reaches in Kashmir during April & May has slowed the progress of work, BRO is committed to completing the task in time.”

As per the statement, Lt Gen Rajeev Chaudhry, VSM, DGBR visited Baltal and Chandanwari today and inspected the progress of work on both Yatra tracks.

He was briefed in detail by CE, Beacon on the status of various tasks being undertaken by BRO and the envisaged completion plan before the commencement of the Yatra 2023.

Speaking on the occasion, DGBR commended the Karamyogis of Project Beacon for the restoration work being executed on the tracks.

He assured everyone that despite the loss of precious time due to inclement weather during April-May, the tracks will be made available to the Civil Administration by June 15 as desired.

He also informed that the restoration works for further improvement of the tracks will continue even after the completion of Yatra this year to facilitate better quality tracks for subsequent years.

Hot this week

Railway Wing Seizes Massive Polythene Consignment Loaded from Delhi

Budgam, Dec 12,: The Railway Wing of Jammu and...

Kashmir Freezes Again as Night Temps Plunge

acebookShare via EmailSrinagar, Dec 12:  Cold wave conditions tightened...

Employee Accused of Using Fake DOB for Illegal Regularisation

Srinagar, Dec 12,: The Special Crime Wing of Crime...

1 Killed, Three Others Injured In Kishtwar Road Accident

Jammu, December 12: Atleast one person was killed while...

Topics

Railway Wing Seizes Massive Polythene Consignment Loaded from Delhi

Budgam, Dec 12,: The Railway Wing of Jammu and...

Kashmir Freezes Again as Night Temps Plunge

acebookShare via EmailSrinagar, Dec 12:  Cold wave conditions tightened...

Employee Accused of Using Fake DOB for Illegal Regularisation

Srinagar, Dec 12,: The Special Crime Wing of Crime...

1 Killed, Three Others Injured In Kishtwar Road Accident

Jammu, December 12: Atleast one person was killed while...

Congress leader and former Union Minister Shivraj Patil passes away

New delhi,Dec 12,: Former Union Minister and Congress leader...

High Court of J&K, Ladakh declares Dec 20 as working day

JAMMU, DECEMBER 11: In a significant demonstration of its...
spot_img

Related Articles

Popular Categories

spot_imgspot_img