DC Srinagar reviews progress of works on Highway Projects in the District

Resolves land issues of Ring Road, Slip Roads, Srinagar-Narbal Road, Lasjan Intersection

Srinagar, Mar 25:The Deputy Commissioner (DC) Srinagar, Mohammad Aijaz Asad Saturday chaired a meeting of Officers, representatives of Beacon and NHAI working on part of Srinagar Ring Road project at Rambirgarh-Pratabgarh, Slip Roads, Srinagar Narbal Road & Loops at Lasjan Intersection here at Conference Hall of DC Office Complex to resolve land issues of major developmental projects taken up to improve Highway connectivity in District.

 At the outset, the Deputy Commissioner was given first hand appraisal about the progress of work on Srinagar-Baramulla-Uri(NH-1) KM-16+500 to 17+400 section of Srinagar Ring Road project at Rambirgarh-Pratabgarh involving 57 kanals and 12 marlas of land acquired under the Project.

 After holding a detailed discussion on the matter, the DC asked for constituting a Committee comprising the Officers of Sericulture, Social Forestry, Beacon and its consultant to assess the cost of trees on the acquired land. The Committee shall submit the report within a week’s time so that necessary compensation in respect of trees is given to the affected to accelerate the pace of work on the project.

 While reviewing the present status of construction of Slip Roads and Loops for smooth flow of traffic at Lasjan intersection, the DC was informed that the structure estimate received from Superintending Engineer PWD(R&B) Circle Srinagar/Budgam has been forwarded to Project Director NHAI.

 The DC was further informed that estimates for left out land and left out structures coming in the Project have also been received from Superintending Engineer PWD(R&B) Circle Srinagar/Budgam and forwarded to NHAI for its authentication.

 On the occasion, the DC asked the NHAI to speed up the process at their end in order to ensure time bound execution of works.

On the occasion, the Deputy Commissioner directed the Officers and concerned executing agencies to speed up the pace of works being carried out on the projects and complete them under set timelines. He called upon them to ensure all major developmental projects are carried without any further delay for the larger public interest.

The DC said that the projects are of immense public importance and are being strictly monitored by higher authorities for the earliest completion. He said timely completion of these projects will prove helpful towards overcoming traffic jams and improving road connectivity to ensure smooth plying of traffic on the highway.

The meeting was attended by Chief Planning Officer, Srinagar, Collector PWD, Tehsildar Shalteng, Tehsildar, Panthchowk, Project Director NHAI, Deputy Officer Commanding Beacon and other concerned.

Hot this week

Food Cart Demolished at Lal Chowk Despite Permission Claim; SMC Action Raises Serious Questions

Srinagar, Nov 12: A newly installed food cart near...

Day After Kulgam Attack: CRPF Special DG Meets LG Manoj Sinha, Security Situation Reviewed

Srinagar, November 12: A day after the Kulgam attack,Sandeep...

Heritage must reach common people, not remain confined to libraries: LG Sinha

Calls for preservation of Kashmir’s manuscripts, cultural legacy and...

Fresh Snowfall in Higher Reaches, Rain in Plains as Kashmir Braces for Two-Day Wet Spell

Srinagar, Nov 12: Fresh snowfall was reported in the...

Search for Missing SPOs Ends in Tragedy; Bullet-Riddled Bodies Recovered in Kishtwar Forests

Kishtwar, Nov 12: The search for two Special Police...

Topics

spot_img

Related Articles

Popular Categories

spot_imgspot_img