Highway 4-Lanning: DC Ramban reviews progress on Nashri – Banihal section,Asks NHAI authorities to expedite work  

RAMBAN, MAY 03:  Deputy Commissioner, Ramban, Mussarat Islam today conducted a virtual meeting with the officers of National Highway Authority of India (NHAI)  to discuss and resolve issues and take stock of the progress on the prestigious Nashri-Ramban and Ramban -Banihal  sections of Jammu – Srinagar National Highway 4- lanning Project.

Additional Deputy Commissioner, Harbans Lal, who is also the Collector, Land Acquisition (National Highway); Project Director, Parshotam Kumar, representatives of construction companies besides other senior officers of district administration attended the meeting.

During the meeting, the issues including land acquisition, shifting of HT towers, maintenance of existing road, land and structure damage compensation cases were discussed. The DC resolved most of the issues and bottlenecks highlighted by the   representatives of construction agencies by passing necessary directions to the concerned officers besides reviewing location-wise issues of land acquisition and compensation cases.

Executing agencies were directed to come up with a comprehensive land acquisition plan and submit indent for the same. They were also asked to take local people on board to resolve the local issues.

While directing the concerned officers to expedite the pace of work, the DC also impressed upon them to adhere to SOPs to contain the spread of Covid infection.

The DC assured NHAI officers of full support of the District Administration to achieve the targets in the completion of the prestigious four laning Project, which will provide better connectivity to people of Jammu and Kashmir.

In light of the directions passed by the Government from time to time, he urged the NHAI and other construction companies to engage local youth in National projects and train them in various skills related to construction engineering, which shall enhance their chances of employability.

Keeping in view of the surge in Covid positive cases, the Deputy Commissioner informed the executing agencies that in order to resolve the issues for hassle-free construction, the District Administration will continue to hold periodic virtual meets.

Hot this week

Srinagar airport expansion misses earlier deadline, completion now targeted for 2031

Srinagar, Sep 9, KNT: The planned expansion of Srinagar...

PM Package employees set Sep 30 deadline over pending transit accommodation

Srinagar, Sep 9,: Kashmiri Pandit employees appointed under the...

Kashmir an ideal destination for filmmaking: Spanish filmmaker at IFFJK

Srinagar, Sept 09: Spanish filmmaker and producer Anna Saura...

Handwara Police busted a terror module run by ex-terrorist operating in Hybrid Mode

Handwara,September 09: Handwara Police received reliable information regarding the...

Topics

PM Package employees set Sep 30 deadline over pending transit accommodation

Srinagar, Sep 9,: Kashmiri Pandit employees appointed under the...

Kashmir an ideal destination for filmmaking: Spanish filmmaker at IFFJK

Srinagar, Sept 09: Spanish filmmaker and producer Anna Saura...

Handwara Police busted a terror module run by ex-terrorist operating in Hybrid Mode

Handwara,September 09: Handwara Police received reliable information regarding the...

J&K to remain largely dry, scattered rain likely through September 20

Srinagar, Sep 9,: Jammu and Kashmir is likely to...

ACB traps Treasury clerk for demanding, accepting Rs 20,000 bribe

Rajouri, Sept 09: The Anti-Corruption Bureau (ACB) on Wednesday...
spot_img

Related Articles

Popular Categories

spot_imgspot_img